In 2025, the BCxA launched the Owners Committee. The Owners Committee represents the owners in the commissioning process (Cx) and offers outreach to other owner groups on Cx's best practices. They are also tasked with creating a program for owners to share experiences and provide input to the training and best practices developed by the Association. This committee will review best practices, templates, and sample documents and help guide the association in providing a better understanding for both CxPs and owners. The members shall advise on the owner’s perspective on topics related to building design and construction, as well as other built environment issues related to commissioning.
What better way to kick off our new committee than with an Owners panel at the 2025 BCxA Conference in Pittsburgh, PA!
The Owners panel consisted of: Wade Berner, Director of Systems Performance & Turner, Massachusetts Institute of Technology. Michael Hoffman, Energy Manager of the Facility Services Utilities Branch, University of Arizona. 2025 Benner Award Winner Rachel Stuckey, Director of Engineering & Commissioning at the University of Rochester. The panel was moderated by Jeremy Bartlett, Facility Commissioning Specialist at The Johns Hopkins University Applied Physics Laboratory.
In the spirit of the 2025 conference goal for audience participation and interaction, we chose to make the panel interactive by posing questions to the audience via the BCxA conference app. The audience’s responses were relayed to the panel, which then provided owner feedback.
Eight poll questions were developed to drive discussion on changes and industry shifts we are seeing in commissioning. The goal was to find where our commissioning providers and owners don’t quite see eye to eye.
1. The Most Underappreciated Phase: Pre-Design, By a Mile
When we asked, “Where is commissioning the most underappreciated by Owners?” the answer wasn’t even close:
Pre-Design Phase – ~72%
Design Phase – ~24%
Construction / Occupancy & Operations – each under 2%
In other words, most respondents feel that owners still don’t fully recognize the value of bringing commissioning to the table early—when performance goals, system concepts, and budgets are being defined.
The poll underscores the ongoing need to educate owners that the cheapest and most effective place to “buy” commissioning value is before design is locked in.
2. How Providers Want to Be Hired: Direct Access to the Owner
In the contracting models, we asked providers which relationship they preferred. The clear favorite:
Contracted directly to the Owner’s Construction Team – ~43%
Direct to Construction Team with reporting to Facilities – ~31%
Direct to Facilities Maintenance Team – ~23%
Direct to the Contractor – ~3%
The message is pretty blunt: commissioning providers want a direct line to the owner, not to be buried in a subcontracting chain under the contractor. There was a difference of opinion by members of the panel, where some found having commissioning providers report to Owner construction teams while others are shifting to having providers report to facilities and maintenance.
3. TAB/BAS as Sub-Consultants? Many Say: “That’s Not Commissioning.”
We also presented two different BIG10 university approaches where trade contractors (TAB and BAS controls) are set up as sub-consultants to the commissioning provider, and asked which made the most sense:
TAB as a sub to the Cx provider – ~43%
BAS controls as a sub to the Cx provider – ~10%
Neither, this isn’t commissioning – ~48%
Almost half the respondents rejected the entire premise, saying that folding these trades under the commissioning provider doesn’t align with what commissioning is supposed to be. The takeaway: many practitioners feel that commissioning should remain an independent, owner-focused function, not just another wrapper for trade management.
4. Split Phases = Uncertain Awards
Given budget constraints and the owner's need to bid separately on the design and construction phases, we asked providers how likely they are to bid on a project if not guaranteed both phases of work.
Highly likely – ~34%
Somewhat likely – ~46%
Not likely – ~20%
Most people are only cautiously optimistic. A significant portion doubt they’ll be carried through from design into construction. That has implications for how deeply a provider invests during early phases—and for owners who may be losing continuity.
5. Load Bank Testing: Still Rare in Commissioning Scopes
On the technical side, we asked: “How often do you see Cx scopes or RFPs require load bank testing of mechanical systems?”
Never – ~48%
Occasionally – ~33%
Starting to see more of it – ~16%
We see this everywhere – ~2%
So, for most respondents, load bank testing is still the exception, not the rule. Given the growing focus on resilience and full-load performance, there’s a real opportunity for owners and designers to more consistently call out load bank testing where it meaningfully validates system capacity and reliability.
6. The Most Underappreciated Deliverables
We then asked, “What commissioning deliverable is the most underappreciated by Owners?”
Site Observation Reports – ~33%
Commissioning Report – ~31%
Training Records – ~28%
Issues Log – ~8%
It’s telling that the core narrative documents—site observations and the final commissioning report—are seen as the most underappreciated. These deliverables tell the story of what was found, fixed, and verified. Yet owners may skim or shelve them, focusing instead on punch lists and closeout checkboxes.
Training records also ranked high as underappreciated, suggesting that the long-term operational benefits of commissioning still don’t get the attention they deserve.
Panel members suggested a dedicated commissioning report page as part of the project closeout process.
7. The Biggest Barrier: Not Money—Engagement
When we asked about the biggest barrier to effective commissioning, the top answer wasn’t commissioning fees as we expected:
Lack of Owner engagement – ~53%
Limited Cx fees – ~23%
Limited Cx scopes of work – ~19%
Inexperience of the Cx provider on new technologies – ~4%
Yes, budgets and scope matter—but more than half of respondents pointed to owner engagement as the single largest hurdle. Even a well-written scope and adequate fee can’t rescue a project where the owner isn’t aligned, present, or empowered to make decisions.
8. What Owners Struggle With Most
Finally, drawing from a BCxA Owners Committee discussion, we asked which challenge was most common among owners:
Project closeout – ~32%
Writing commissioning SOW/RFP – ~31%
Keeping up with commissioning across multiple projects – ~20%
Finding local qualified providers – ~17%
Project closeout and scoping/RFP development are essentially tied at the top, pointing to a need for better tools, templates, and guidance for owners at both ends of the project lifecycle: setting commissioning up correctly at the start and landing it cleanly at the finish. The audience's perception of owner challenges aligns with those of many owners who participated in the owner committee polling.
Putting It All Together
Across these questions, a consistent story emerges:
- Commissioning is still undervalued at the pre-design stage, where it could do the most good.
- Providers want direct relationships with owners and clear independence from contractors.
- Owners and practitioners are still negotiating what commissioning is (and is not).
- Technical expectations like load bank testing are far from standard, even as system complexity grows.
- The true barriers are less about line items and more about engagement, clarity, and follow-through.
If we want better-performing buildings, we can’t treat commissioning as a late-stage checkbox. The poll results are a reminder that the biggest wins happen when owners, designers, and commissioning providers align early, communicate often, and treat the process as a strategic investment—not an afterthought.